Data and reporting · Free Word and Excel template

Daily Equipment Report Template for Site Engineers

A daily equipment report the site engineer completes every shift: one line per machine with working, idle, standby and breakdown hours, output, fuel and hour meter, plus breakdowns, movements, site checks and sign-off. The Excel log turns the reports into availability, utilization and output per working hour against plan for each machine.

Free: enter your name, email and job title and we email you the file. The report opens in Word, Google Docs and LibreOffice; the log works in Excel, Google Sheets and LibreOffice Calc, with no macros.
  • Report on 2 A4 pages
  • Hours by state for every machine
  • Availability, utilization, output vs plan
safee-daily-equipment-report-en.xlsx
DateMachineWork hIdle hStandby hBreakdown hOutput% of planFlags
10-18EX-018.51.00.501,240 BCM97%
10-18EX-026.02.51.50840 BCM93%Hour meter differs; High idle
10-18WL-017.51.51.001,650 LCM110%Tracker differs
10-19EX-017.00.50.52.01,010 BCM96%
10-20WL-017.02.01.001,080 LCM77%Output below plan; High idle
10-20DZ-016.51.01.01.51,600 BCM98%Breakdown without cause
Example rows for 10-hour day shifts. The alert limits (0.5 h, 80% of plan, 20% idle) are examples on Settings.
What's in the file

A report for the site and a log for the office

The site engineer fills the Word report on site each shift. The office enters it in the Excel log, which checks the hours and works out the measures for every machine.

  1. 01

    Report: project and day

    Project or package, report number, date, shift and hours, site engineer, weather and maximum temperature, and whether the midday work ban hours were kept.

  2. 02

    Report: equipment on site

    Twelve lines: machine and type, operator and ID number, activity and zone, working, idle, standby and breakdown hours, output with its unit, fuel and the hour meter at the end.

  3. 03

    Report: breakdowns, movements and checks

    Breakdowns and delays with times, cause and action, delays not caused by machines, machines arrived, left or moved, eight site checks, the plan for tomorrow and three signatures.

  4. 04

    Excel: equipment register

    Up to 40 machines with their type and the planned output per working hour from the project plan or the productivity calculator.

  5. 05

    Excel: daily log

    One row per machine per shift. It works out availability, utilization, idle share, output per working hour, % of plan, meter and tracker differences and fuel per working hour and per unit, with six flags.

  6. 06

    Excel: monthly summary

    Hours, availability, utilization, idle share, output against plan and fuel by machine and by type for the month, totals by month for the year, and a chart.

What is a daily equipment report?

A daily equipment report records every machine on a site for one shift: who operated it, what it did and where, how many hours it worked, idled, waited and stood broken down, what it produced and how much fuel it took. Site engineers send it to the project manager, the equipment manager and often the client.

Collected day after day, the reports show which machines earn their place on site. The log in this template turns them into availability and utilization, the two measures equipment managers use, and compares each machine's output with the plan.

How to use the daily equipment report

  1. Register the machines in the Excel log with the planned output per working hour, from the project plan or the Excavator, Loader & Dozer Productivity Calculator.
  2. Complete one report per shift, with a line for every machine on site, also those that did not work.
  3. Split the shift hours into working, idle (engine on, no work), standby (engine off, ready) and breakdown. They should add up to the shift.
  4. Read the hour meter at the end of the shift and note the fuel issued to each machine.
  5. Write the cause of every breakdown and delay, and the machines that arrived, left or moved.
  6. Enter the report in the log the same day, clear the flags and review the monthly summary.

How does the log calculate availability and utilization?

Availability = (required hours − breakdown hours) ÷ required hours Utilization = working hours ÷ (required hours − breakdown hours) Idle share = idle hours ÷ (working + idle hours) Output per work hour = output ÷ working hours, % of plan = output per work hour ÷ planned Meter difference = (meter end − meter start) − (working + idle hours) Fuel per unit = fuel issued ÷ output

Availability and utilization follow Mike Vorster's definitions: availability is the time a machine is required and able to work divided by the time it is required, and utilization is the time it works divided by the time it is required and able to work. The alert limits on Settings are your choice.

Source: Mike Vorster, Understanding Equipment Utilization and Availability Metrics, Construction Equipment, 30 July 2025. Source: Construction Equipment. Last reviewed 21 October 2026.

Worked example: three day shifts on an earthworks package

The example has six machines on 10-hour day shifts from 18 to 20 October 2026. Planned outputs are examples.

  • EX-01 excavator: 30 required hours, 23.5 working, 3 idle, 1.5 standby and 2 of breakdown for a burst hose. Availability (30 − 2) ÷ 30 = 93%; utilization 23.5 ÷ 28 = 84%.
  • It moved 3,430 BCM: 3,430 ÷ 23.5 = 146 BCM per working hour, 97% of the planned 150. Its 730 L of fuel is 31.1 L per working hour and 0.21 L per BCM.
  • EX-02 on 18 October: the hour meter ran 9.3 hours but working plus idle was 8.5, a 0.8-hour difference over the 0.5-hour allowance. Idle was 2.5 of 8.5 engine hours, 29%, while it waited for trucks.
  • WL-01 on 20 October: 1,080 LCM in 7 working hours is 154 LCM an hour, 77% of plan, with 22% idle.
  • DZ-01 on 20 October shows 1.5 hours of breakdown with no cause written, so the row is flagged until the engineer adds it.

Common mistakes with daily equipment reports

  • Leaving out machines that did not work. Standby and breakdown machines still cost money and lower utilization.
  • Counting idle as working. An engine running while the machine waits is not production, and it burns fuel.
  • Hours that do not add up. Without a full split of the shift, availability and utilization mean little.
  • Output with no unit. Bank m³, loose m³, tonnes and loads cannot be added together.
  • No cause for breakdowns. Repeated causes are what the maintenance team needs to see.
  • Filling the report the next morning. Hours and output written from memory are rounded.

What the template does not do

The log works with what the site engineer records; it does not read the machines. Planned outputs and alert limits come from your plan and your choices. A gap against plan is a question for the site, not a verdict on the operator. For hire invoices, compare hours with the Equipment Timesheet and Hours Reconciliation Template; for when machines arrive and leave, use the Project Equipment Plan and Histogram.

Related Safee solution

Get machine hours and operators from tracking

Safee's Equipment Activity Status reads a digital input of the tracking unit on each machine and shows it as active or not active, and the Equipment Activity report gives each machine's active and non-active duration. With the Dynamic Driver module and an iButton or RFID reader, each shift is recorded against the operator who started the machine with his ID.

  • Equipment Activity report with active and non-active time for machines that work in place.
  • Dynamic Driver to link each machine's hours to the operator's ID.
  • Geofence entry and exit for each zone and site you draw.
  • Excel export and scheduled reports.
FAQ

Questions about daily equipment reports

Want each machine's hours and operator without waiting for the daily report? Talk to Safee.

What should a daily equipment report include?

The project, date and shift; every machine on site with its operator, activity, zone, working, idle, standby and breakdown hours, output, fuel and hour meter; breakdowns and delays; equipment movements; site checks; and signatures.

What is the difference between idle and standby?

Idle means the engine is running but the machine is not working, so it burns fuel. Standby means the machine is fit and ready with the engine off, waiting for work. Both count against utilization.

How are equipment availability and utilization calculated?

Availability = (required hours − breakdown hours) ÷ required hours. Utilization = working hours ÷ (required hours − breakdown hours). These follow Mike Vorster's definitions in Construction Equipment.

Where does the planned output per hour come from?

From your project plan or tender, or from the Excavator, Loader & Dozer Productivity Calculator, which works out output in m³ per hour from bucket size, fill factor and cycle time.

Is this the same as the equipment timesheet?

No. The daily report records what every machine did and produced on site. The timesheet checks the hours of hired machines against the hour meter, the tracker and the supplier's invoice.

Do the files work in Google Docs and Google Sheets?

Yes. Upload the .docx and .xlsx files to Google Drive and open them there. They also work in Word, Excel and LibreOffice, with no macros.

Next step

See every machine's working time without the paperwork

Bring a week of daily equipment reports, and we will show you how Safee's equipment activity and driver ID records cover the same machines and days.

Related tools and templates

Measure site equipment every day