What is a site equipment allocation plan?
A site equipment allocation plan shows which machine is assigned to which site and for which dates. For a contractor running several projects it is where equipment requests meet the equipment you have: it shows when two sites want the same excavator, when a machine will be free for the next job, and what each site's equipment will cost.
Without one, machines are promised twice, idle machines stay on sites that no longer need them, and hired machines are brought in while owned ones stand in the yard.
How to use the allocation plan
- Set up site codes, managers, equipment types, currency and the board start date. Use each site's geofence name as its code if you track the machines.
- List the equipment with a cost per day: owning and running cost for owned machines, the daily hire rate for hired ones.
- Enter each request as a row with machine, site, dates and activity, status Requested.
- Check the weekly board for "!!" cells and free machines, then confirm or move requests.
- Update the status to On site when the machine arrives and Released when it leaves, with the first date seen at site from tracking.
- Review weekly: flags on the plan, free machines on the equipment list, the planned cost per site on the Summary.
How does the plan work out clashes and cost?
Released periods are left out of clashes, the board, today's site and planned cost. "Not seen at site" applies to Confirmed and On site periods whose start has passed by the days on Settings with no date seen.
Worked example: eight machines on 21 October 2026
- Excavator EX-01 is on Riyadh Project 1 until 30 November, but Dammam Project 3 has requested it from 20 November. The two periods overlap for 11 days, so both rows are flagged Double-booked and the board shows "!! DMM-P3" for those weeks.
- Bulldozer DZ-01 was due off Dammam Project 3 on 15 October but is still marked On site: Past end date, not released. Either it is still needed and the plan is wrong, or it should be moved.
- Wheel loader WL-01 is On site at Riyadh from 15 October, but no date seen at the site is recorded: Not seen at site.
- On the Summary, Riyadh Project 1 has 3 machines on site today, and three machines are free today.
How to make the plan work
- One owner of the plan. Site managers request; one coordinator confirms, so there is one version.
- Short periods, updated often. Book the dates the work needs, and extend when it is late, rather than booking machines for the whole project.
- Use owned machines first. Before hiring, look for free owned machines on the board in the same weeks.
- Check arrivals against tracking. A geofence per site tells you when a machine really arrived and left.
- Price the idle weeks. A machine with a low share of allocated days is a candidate to sell, off-hire or move.
What the template does not do
The plan shows what you enter; it does not read tracking data or optimize the allocation. Planned cost is an estimate from the cost per day and does not include moves between sites. The board shows 26 weeks from the start date. To work out a cost per day for owned machines, use the Equipment Hourly Cost Calculator; to track hours on each machine, the Equipment Timesheet template.