Budget and cost · Free Excel template

Project Equipment Plan and Histogram

Plan when each excavator, loader, crane, pump and generator arrives on the project and when it leaves. The workbook draws the weekly equipment histogram, planned against actual units on site, spreads the cost over the months of the project and flags machines that are late to arrive or overdue to leave.

Free: enter your name, email and job title and we email you the file. Works in Excel, Microsoft 365, Google Sheets and LibreOffice Calc, with no macros.
  • 200 equipment rows
  • 104-week histogram
  • Monthly cost and delay flags
safee-project-equipment-histogram-en.xlsx
No.TypeQtyPlanned on sitePlanned off siteActual on siteStatusPlanned cost
EX-01Excavator22026-09-132027-02-282026-09-15On site111,123
DT-01Dump truck62026-09-132027-02-282026-09-14On site208,594
MC-01Mobile crane12026-10-042026-10-152026-10-04Demobilization overdue12,343
RL-01Roller22026-10-182027-04-30Mobilization late75,649
CP-01Concrete pump12026-10-252027-06-30Mobilizing soon87,593
Example rows as of 21 October 2026, in USD. Example rates are illustrations, not market rates.
What's in the file

One plan, a weekly histogram and a monthly budget

You enter each machine once, with its planned dates and its rate. The histogram, the monthly cost and the status of every machine are calculated from that list.

  1. 01

    Equipment plan

    One row per machine or group: type, size, quantity, own or hired, supplier, activity or zone, planned and actual on-site and off-site dates, rate basis, rate and tracker fitted.

  2. 02

    Cost and status per row

    Planned days, cost per day per unit, planned cost, days and cost to date, and a status: Planned, Mobilizing soon, Mobilization late, On site, Demobilization overdue or Demobilized.

  3. 03

    Weekly histogram

    Units planned on site each week for 104 weeks by equipment type, units actually on site up to today, the difference, and a stacked chart with the actual line.

  4. 04

    Summary

    Peak units on site and the week it falls in, units on site today, total planned cost, cost to date, and the number and cost of machines past their off-site date.

  5. 05

    Monthly cost

    Planned cost for 36 months by equipment type, the monthly total and the cumulative total, with a stacked chart for the project budget and cash flow.

  6. 06

    Settings

    Project name and start date, as-of date, currency, working days a week, mobilization notice and the lists of equipment types, own or hired and rate basis.

What is an equipment histogram?

An equipment histogram is a bar chart of how many machines a project needs over time: time runs along the bottom and the number of units up the side, with one color for each type of equipment. Mastt describes the resource histogram the same way and notes the pattern of phased projects: a gradual build-up, a peak, then planned demobilization.

Contractors use it to agree the equipment plan with the client, book hired plant ahead of the peak, and see when machines should leave site. Adding the actual dates turns the plan into a weekly check of what is really on site.

How to use the equipment plan and histogram

  1. Set up the project: name, start date (week 1 starts on it), currency, working days a week and how many days ahead you want the mobilization notice.
  2. Enter the plan: one row per machine or group of identical machines, with the planned on-site and off-site dates from the program of works.
  3. Enter the rate: monthly, weekly, daily or hourly, as in the hire agreement, or an internal rate for your own machines.
  4. Review the histogram and the budget with the planning and commercial teams before you place hire orders.
  5. Record the actual dates from delivery and return notes, or from the tracking system, as each machine arrives and leaves.
  6. Review the statuses every week: chase late arrivals, and return or reassign machines past their off-site date.

How does the template calculate the histogram and the cost?

Units planned in a week = total quantity of rows whose planned dates cover any day of the week Units actual in a week = same, with the actual on-site date and the actual off-site date (or today) Cost per day per unit = monthly × 12 ÷ 365 · weekly ÷ 7 · daily × working days ÷ 7 · hourly × hours a day × working days ÷ 7 Planned cost = quantity × cost per day × (planned off-site − planned on-site + 1) Cost of overdue days = quantity × cost per day × (as-of date − planned off-site)

The monthly cost spreads each row over the calendar days it falls in each month. Statuses compare the dates with the as-of date: a machine with no actual on-site date after its planned date is late, and a machine still on site after its planned off-site date is overdue.

Source for the histogram method: Arlene Hidalgo, What Is a Resource Histogram?, Mastt, 3 March 2025. Source: Mastt. Last reviewed 21 October 2026.

Worked example: a roads and earthworks package

The example rows start on 6 September 2026 and use rates in USD that are illustrations, not market rates. On 21 October 2026:

  • The plan peaks at 20 units in the week starting 6 December 2026, when the tower crane joins the earthworks fleet. 16 units are on site on 21 October.
  • Two excavators at 10,000 a month cost 10,000 × 12 ÷ 365 = 328.77 a day each. Over the 169 planned days that is 2 × 328.77 × 169 = 111,123.
  • The 50 t mobile crane at 1,200 a day, six working days a week, costs 1,028.57 a calendar day. It was due off site on 15 October and is still there: 6 days overdue, 6,171 so far.
  • The two rollers were due on 18 October and have not arrived: Mobilization late, 3 days. The concrete pump is due on 25 October: Mobilizing soon.
  • The total planned cost is 981,393, with the highest month in December 2026.

Common mistakes with equipment plans

  • Planning by type only. Without a row per machine or group you cannot follow arrivals, returns and costs.
  • Never entering actual dates. The plan then shows what was intended, not what is on site and being paid for.
  • Keeping hired plant past its dates. Machines that finished their work keep costing hire until someone returns them.
  • Mixing rate bases. A daily rate written in the monthly column inflates the budget many times over.
  • One histogram for the whole contract. Large projects need a plan per package or zone, then a combined view.

What the template does not do

The template counts and costs machines from the dates and rates you enter; it does not schedule the work or check that a machine is idle. Planned cost leaves out fuel, operators and mobilization charges unless your rate includes them. A week counts a machine on site on any day of it, so short stays show as full weeks. The charts show the 15 listed equipment types; types you add in empty rows appear in the tables. To estimate how many machines a quantity needs, use the Excavator, Loader & Dozer Productivity Calculator, and to check daily hours and hire invoices, use the Equipment Timesheet and Hours Reconciliation Template.

Related Safee solution

Get actual on-site dates and activity from tracking

Draw a geofence around the project site, and Safee's Vehicle Geofence Movement Details report lists the entry and exit times of each machine fitted with a tracking unit, so the actual dates in this plan come from records. The Equipment Activity report then shows how long each machine on site was active.

  • Geofence entry and exit for each machine and site you choose.
  • Equipment Activity report with active and non-active time from a signal on the machine.
  • Asset Utilization report with days with and without trips for trucks and vehicles.
  • Excel export and scheduled reports.
FAQ

Questions about equipment plans and histograms

Want the actual arrival and departure of every machine without chasing site reports? Talk to Safee.

What is an equipment histogram in construction?

A chart of the number of machines planned on site in each week or month of the project, usually stacked by equipment type. It shows the build-up, the peak and when machines should leave.

How do I make an equipment histogram in Excel?

List each machine with its planned on-site and off-site dates, count the units whose dates cover each week, and chart the counts as stacked columns. This template does the counting with SUMIFS and draws the chart for you.

What is the difference between mobilization and demobilization?

Mobilization is bringing a machine to site and making it ready to work. Demobilization is removing it from site when its work is done. Both dates drive hire cost.

How is the monthly equipment cost calculated?

Each rate is turned into a cost per calendar day, multiplied by the quantity and by the days of each month between the on-site and off-site dates. Monthly rates use rate × 12 ÷ 365 a day.

Can I compare the plan with what is actually on site?

Yes. Enter the actual on-site and off-site dates and the histogram shows the actual units next to the planned units every week up to today, with the difference.

Does it work for a manpower histogram too?

The counting works the same way for people, but the rates, statuses and lists are set up for equipment. Rename the types on Settings if you want to try it for crews.

Do the files work in Google Sheets?

Yes. Upload the .xlsx file to Google Drive and open it there. It also works in Excel and LibreOffice, with no macros.

Next step

See which machines are really on your sites

Send us your equipment plan, and we will show you how Safee's geofence and equipment activity reports record each machine's arrival, departure and working time.

Related tools and templates

Plan and control site equipment

Get the report

Enter your details and we will email you the file.

Use your real name so the file arrives addressed to you. Don't worry, we won't flood you with emails or calls.

Scroll to Top