Utilization · Free calculator

Haul Truck Cycle & Match Calculator

Work out haul truck cycle time from loader passes, loading, haul, dump and return times. Then see how many trucks each loader needs, the match factor of your fleet, the tonnes it moves per hour and shift, the cost per tonne and the fleet needed for a target.

  • Runs in your browser
  • Your own site figures
  • Formulas shown below

Enter one truck, one loader and the haul route. The defaults are an example of a quarry running 40-tonne trucks; replace them with your site's figures.

Truck and loader
t

From the truck specification or its actual weighed load. Example value.

t

Bucket volume × loose density of the material, or from the loader specification. Example value.

%

Pit & Quarry's handbook gives 75 to 90% for loading blasted rock.

s

Fill, swing, dump into the truck and return. Time it on site. Example value.

Route and fixed times

From the loading point to the dump point. Example value.

Average over the whole road, grades and bends included. Example value.

Example value.

min

Maneuvering into the loading position. Example value.

min

Example value.

min

Queues at a weighbridge or crossings as seen on site. Waiting caused by too few loaders is worked out in the Match tab.

How this is calculated
Load per pass = bucket rated load × fill factor Passes = round up (truck payload ÷ load per pass) Loading time = passes × loader cycle per pass Truck cycle = spot + loading + haul loaded + dump + return empty + waiting

Full methodology is below.

Truck cycle timeBased on values entered

Take this to the site manager

Report with the inputs, truck cycle, match factor, output and fleet needed.

Haul cycle report

Get the full report for your site team

  • Truck cycle by part and loader passes
  • Trucks per loader and match factor
  • Output per hour and shift, cost per tonne
  • Fleet needed for the target
  • Methodology, sources and next steps

What is haul truck cycle time?

Haul truck cycle time is how long one truck takes to go round once: spot at the loader, get loaded, haul to the dump, dump and return empty. The King Saud University course on loading and hauling splits it into fixed time (spot, load, maneuver and dump) and variable time (haul and return), because the fixed part barely changes while the variable part grows with distance and road condition.

From the cycle and the loading time the calculator works out how many trucks one loader can keep busy, the match factor of your fleet, the tonnes it moves per hour and per shift, and the fleet needed for a target.

Why does the truck–loader match matter?

  • Too few trucks: the loader stands waiting between trucks, and you pay for an expensive machine and operator doing nothing.
  • Too many trucks: trucks queue at the loader, burning fuel and driver hours without moving material.
  • Distance changes the answer: as the pit deepens or the dump moves, the cycle grows and the same fleet falls out of balance.
  • Half buckets cost time: Pit & Quarry notes that loading half buckets takes as long as loading full ones, so the number of passes matters.

What inputs do you need?

InputWhere to find itTip
Payload and bucket loadEquipment specifications, weighbridge recordsUse the real average load if trucks run under or over their rating.
Fill factorBucket load weighed against rated loadPit & Quarry gives 75 to 90% for blasted rock.
Loader cycle per passA stopwatch at the face, video from the siteTime 20 or more passes and use the average.
Distance and speedsSite plan, tracking data of the trucksAverage speed per direction, not the site speed limit.
Spot, dump and waiting timesObservation, tracking data with loading and dump areasRecord a full shift: waiting changes over the day.
Productive minutes per hourShift reports: breaks, refueling, shift changeMeasured minutes are better than a rule of thumb.

How is the cycle and the match calculated?

Passes and loading time

Load per pass = bucket rated load × fill factor Passes = round up (truck payload ÷ load per pass) Loading time = passes × loader cycle per pass

Pit & Quarry divides the truck's rated payload by the desired number of passes to size the bucket, multiplies the rated bucket capacity by the fill factor for the material, and calls three passes ideal, with four or five generally acceptable for larger haulers.

Truck cycle

Haul time = distance ÷ speed loaded × 60 Return time = distance ÷ speed empty × 60 Truck cycle = spot + loading + haul + dump + return + other waiting

Trucks per loader and match factor

Trucks per loader = truck cycle ÷ loading time (round up) Match factor = (trucks × loading time) ÷ (loaders × truck cycle)

The trucks-per-loader rule is Equation 4-16 of the King Saud University course: haul unit cycle time ÷ load time, rounded up. A match factor of 1 means neither waits; below 1 the loaders wait for trucks; above 1 trucks queue at the loaders, as set out in the match factor literature (Journal of Mining & Environment, 2025).

Output and cost per tonne

Truck capacity = trucks × payload × 60 ÷ truck cycle (t/h) Loader capacity = loaders × payload × 60 ÷ loading time (t/h) Output = lower capacity × productive minutes ÷ 60 Cost per tonne = (trucks × truck cost per hour + loaders × loader cost per hour) ÷ output

Sources

  • King Saud University, CE 419, Chapter 4: Loading and Hauling, part 3 (cycle time, Equations 4-14 to 4-17, job efficiency examples). Source: KSU.
  • M. Mohtasham, Development of a Match Factor for Optimizing Haulage Fleet Efficiency in Open-Pit Mining Operations, Journal of Mining & Environment, 2025. Source: JME.
  • Pit & Quarry University, Hauling handbook lesson (passes, bucket sizing, fill factor 75 to 90% for blasted rock). Source: Pit & Quarry. Last reviewed 21 October 2026.

Worked example: one loader and six 40-tonne trucks

The defaults are examples; replace them with your site's figures.

  • A 16 t bucket at 85% fill carries 13.6 t a pass, so a 40 t truck needs 3 passes. At 30 seconds a pass, loading takes 1.5 min.
  • 2.5 km at 20 km/h loaded is 7.5 min and at 30 km/h empty 5 min. With 0.5 min spot and 1 min dump the cycle is 15.5 min, 81% of it travel.
  • One loader can keep 15.5 ÷ 1.5 = 10.3, so 11 trucks, busy. With 6 trucks the match factor is 0.58: the loader waits 42% of the time.
  • Six trucks move 6 × 40 × 60 ÷ 15.5 = 929 t/h at full time, or 774 t/h at 50 productive minutes: 7,742 t in a 10-hour shift.
  • At $60 an hour per truck and $100 for the loader the fleet costs $460 an hour, or $0.59 a tonne; with 11 trucks the loader becomes the limit and the cost falls to $0.57 a tonne.
  • For 10,000 t a shift you need 1,200 t/h while working: 1 loader and 8 trucks.

How to read your results

  • Match factor below 1: trucks are the limit. Add trucks, shorten the haul or speed up the road before buying a bigger loader.
  • Match factor above 1: the loader is the limit and trucks queue. Fewer trucks move the same tonnes, or a second loading point uses them.
  • Travel share of the cycle: when haul and return dominate, road condition, grades and speed matter more than loader speed.
  • Cost per tonne: compare the current fleet with the matched one; the cheapest fleet is not always the one with no waiting.

How to shorten the cycle

  • Load in three or four passes: size the bucket to the truck and keep the fill factor up.
  • Keep haul roads in shape: Pit & Quarry notes that a 5% rise in rolling resistance can cut production by 10%.
  • Do not overload or underload: check loads on the weighbridge and with the Axle Load Checker for road trucks.
  • Measure, then rebalance: record real cycles by truck and shift, and move trucks between loaders as distances change.
  • Know the machine cost: work out the hourly cost of trucks and loaders with the Equipment Hourly Cost Calculator.

Assumptions and limits

The calculator uses averages: every truck has the same payload, speed and cycle, and arrivals are evenly spaced, so real queues are longer than the averages suggest when cycles vary. The loader is assumed to load one truck at a time. Output is the lower of truck and loader capacity times productive minutes; breakdowns, blasting delays and weather stops need to be in the productive minutes. All defaults are examples, not equipment data. Use the result to plan and compare, then confirm it with measured cycles.

Related Safee solution

Measure every truck's cycle from its recorded trips

Draw a geofence around the loading area and one around the dump, and Safee's Geofence-based Voyage report splits each truck's movement into trips with their times and distances. The cycle times in this calculator then come from your data, not estimates.

  • Geofence-based Voyage report where a voyage starts when the truck leaves the start geofence and ends when it returns, with the entry time of each destination geofence and the distance.
  • Equipment Activity Status from a digital input of the tracking unit on the machine, shown as active or not active.
  • Equipment Activity report with the active and non-active duration of each machine on each trip.
  • Excel export of the trip records you select, to analyze cycles by truck and shift.
Questions

Questions about haul truck cycle and match

Need help measuring your truck cycles? Talk to Safee.

How do you calculate haul truck cycle time?

Add the fixed times, spot at the loader, loading and dump, to the variable times, haul loaded and return empty, each equal to distance ÷ average speed. Loading time is the number of passes × the loader cycle per pass. Add any regular waiting you see on site.

How many trucks does one loader need?

Divide the truck cycle time by the loading time and round up. With a 15.5-minute cycle and 1.5 minutes of loading, one loader can keep 11 trucks busy. Fewer trucks leave the loader waiting; more trucks queue.

What is the match factor?

The match factor compares truck arrivals with loader capacity: (trucks × loading time) ÷ (loaders × truck cycle). At 1 neither waits. Below 1 the loaders wait for trucks; above 1 trucks wait at the loaders.

How many loader passes should fill a truck?

Pit & Quarry's hauling handbook calls three passes ideal and four or five generally acceptable for larger haulers. Size the bucket by dividing the truck's rated payload by the passes you want.

What fill factor should I use?

Your own, from weighed buckets, is best. Pit & Quarry gives 75 to 90% for a loader digging blasted rock. Loose, easy material fills more; large blocky rock fills less.

Does the calculator work for road trucks and tippers?

Yes, for any loader-and-truck operation: quarries, construction earthworks, sand and aggregate supply. For long road hauls, enter the road distance and average speeds, and check axle loads separately.

How can I measure real cycle times?

Time a full shift with a stopwatch, or use tracking data: a geofence around the loading area and one around the dump give the time between each entry and exit. Measured cycles by truck and hour show where the waiting is.

Let's look at your site numbers

Know the real cycle of every truck on your sites

Tell us how many trucks and loaders you run and where they load and dump, and we will show you how Safee records each truck's trips and each machine's activity.

Related tools and resources

Move on to your next fleet question

Get the report

Enter your details and we will email you the file.

Use your real name so the file arrives addressed to you. Don't worry, we won't flood you with emails or calls.

Scroll to Top