Trips & operations · Free tool

Ready-Mix Concrete Truck Planner

Work out how many truck mixers a continuous pour needs from the placement rate, load and distance to site, plus the truck interval, loads, pour time and the time from batching to the end of discharge against the 90-minute limit, with a load-by-load dispatch schedule.

  • Runs in your browser
  • Your own project figures
  • Formulas shown below

Enter the pour, the truck mixer and the distance from the plant to the site. The defaults are an example of a pumped pour; replace them with your project's figures.

The pour
m³

From the drawings, with the waste margin you use. Example value.

m³ / h

What the pump or crane and the crew can actually place per hour. Example value.

m³

The load you actually send, not the drum's maximum. Example value.

min

Use the limit in your project specification. 1½ hours is a common example; hot weather may call for less.

Plant and road
min

From batching to the truck leaving. Example value.

km

One way, on the road actually used. Example value.

km/h

With signals and traffic at the pour time. Example value.

km/h

Example value.

min

Gate, positioning at the pump and the slump test. Example value.

min

Example value.

m³ / h

Leave empty if the plant does not limit the pour.

How this is calculated
Discharge time = load ÷ placement rate × 60 Truck interval = the longest of discharge time, loading time and plant time per load Round trip = loading + haul + time on site + discharge + washout + return Trucks needed = round up (round trip ÷ interval) Delivery time = loading + haul + time on site + discharge

Full methodology is below.

Truck mixers neededBased on values entered

Send the plan to the plant and the site

Report with the inputs, trucks needed, interval and the dispatch schedule for every load.

Pour plan

Get the full pour plan

  • Truck mixers needed and the interval
  • Truck round trip by part
  • Batching to end of discharge against the limit
  • Dispatch schedule for every load
  • Methodology, sources and next steps

How many concrete trucks do you need for a pour?

A continuous pour needs a truck mixer arriving every time the previous one finishes discharging. The truck interval is set by how fast the pump or crane can place a load. Each truck then takes a round trip: loading at the plant, the haul to site, waiting and testing, discharge, washout and the return. Trucks needed = round trip ÷ interval, rounded up. Caltrans' Deck Construction Manual works the same example: a 75-minute round trip and a 14-minute interval give 5.4, so six trucks.

The planner also checks each load against a time limit from batching to the end of discharge, and builds a load-by-load dispatch schedule that shows what a stoppage on site does to the trucks already on the road.

Why does truck planning matter for a pour?

  • Too few trucks: the pump and the crew wait between loads, and cold joints become a risk on a long pour.
  • Too many trucks: trucks queue on site and the concrete in them gets older while it waits.
  • Distance and traffic: a longer haul needs more trucks for the same pour, and traffic at the pour time changes the answer.
  • Time limits: The current ASTM C94 (C94/C94M-24d) no longer sets a fixed time: the purchaser states the limit, or the producer sets one and tells the purchaser before delivery. Many specifications still use 1½ hours and 300 drum revolutions, for example HCAI PIN 82 in California. Late loads may be rejected.

What inputs do you need?

InputWhere to find itTip
Volume to pourDrawings and the pour planAdd the waste margin you use.
Placement ratePump or crane and crew on similar poursUse the rate achieved, not the pump's maximum.
Load per truckPlant dispatch, delivery ticketsThe load sent, often below the drum capacity.
Loading time, washoutPlant records, delivery ticketsTime several trucks.
Distance and speedsRoute at the pour time, tracking data of the mixersNight and morning traffic differ.
Time limitProject specification1½ hours is the example; enter the limit in your specification. Hot weather may shorten it.

How are trucks and the schedule calculated?

Interval and round trip

Discharge time = load ÷ placement rate × 60 Interval = the longest of discharge time, loading time and plant time per load Round trip = loading + haul + time on site + discharge + washout + return

Trucks needed and delivery time

Trucks needed = round up (round trip ÷ interval) Loads = round up (volume ÷ load) Delivery time = loading + haul + time on site + discharge Farthest site within the limit = (limit − loading − time on site − discharge) × speed loaded ÷ 60

The trucks-needed rule is the worked example in section 5-1.2 of Caltrans' Deck Construction Manual: trucks per hour = pour rate ÷ truck load, and trucks needed = round-trip time ÷ the interval between trucks. Section 5-1.4 lists the 90-minute rule and notes it can be shorter on a hot day.

Dispatch schedule

Planned batching of load n = pour start + (n − 1) × interval − (loading + haul + time on site) Actual batching = latest of planned time, end of previous loading, first truck back at the plant Discharge start = later of ready on site and end of previous discharge (+ stop) Age at end of discharge = end of discharge − batching

Sources

  • California Department of Transportation (Caltrans), Deck Construction Manual, Chapter 5, Concrete Placement and Consolidation, October 2015, sections 5-1.2 (delivery rate) and 5-1.4 (90-minute rule). Source: Caltrans.
  • California Department of Health Care Access and Information (HCAI), PIN 82: Ready Mix Concrete Placement Times, effective 9 October 2025 (discharge within 1½ hours and 300 drum revolutions; it notes that ASTM C94/C94M-24d no longer gives a specific time limit). Source: HCAI. Last reviewed 21 October 2026.

Worked example: a 120 m³ pumped pour

The defaults are examples; replace them with your project's figures.

  • A 9 m³ load at 30 m³/h discharges in 18 minutes, so a truck is needed every 18 minutes.
  • Round trip: 8 min loading + 25.7 min haul (15 km at 35 km/h) + 10 min on site + 18 min discharge + 10 min washout + 20 min return = 91.7 minutes.
  • Trucks needed: 91.7 ÷ 18 = 5.1, so 6 truck mixers. The pour takes 14 loads (the last one 3 m³) and about 4 hours.
  • Delivery time: 8 + 25.7 + 10 + 18 = 61.7 minutes, 28 minutes inside a 90-minute limit. Sites up to 31.5 km away stay within it at these speeds.
  • Starting at 05:00, the first truck is batched at 04:16 and the pour ends at 09:00. With only 4 trucks the pump waits about an hour in total and the pour ends at 09:59.
  • If the pump stops for 45 minutes after load 4, loads 5 to 10 are already on the road and reach about 107 minutes from batching: 6 loads over the limit.

How to read your results

  • Interval set by the site: the usual case. More trucks than needed only queue.
  • Interval set by the plant: the plant cannot feed the placement rate. Plan the pour at the plant's rate or use a second plant.
  • Delivery time close to the limit: a little traffic or a short wait on site pushes loads over it. Shorten the haul or the waiting.
  • Loads over the limit after a stop: the dispatcher needs to hold loads at the plant as soon as the site stops.

How to keep a pour on time

  • Agree the interval with the plant before the pour, and confirm it with the first two loads.
  • Tell the plant at once about any stop, so loads are held before batching.
  • Check real haul times: time the route at the pour hour, or use the trip times of the mixers.
  • Plan hot-weather pours early: follow the project specification for concrete temperature and time limits. For outdoor work in summer, see the Midday Work Ban Shift Checker.

Assumptions and limits

The planner uses average times: every truck carries the same load (except the last), drives at the same speeds and spends the same time on site, and one truck discharges at a time. The plant is treated as one loading point. The time limit is checked from batching to the end of discharge; drum revolutions, concrete temperature and slump are not checked. In the stoppage scenario the plant keeps sending loads on the planned times. All defaults are examples, not project or plant data. Use the result to plan, then follow your project specification and the plant's instructions.

Related Safee solution

Know the real delivery time of every load

Draw a geofence around the plant and one around each site, and Safee's Geofence-based Voyage report splits each truck mixer's movement into trips with departure, arrival and return times. The haul and site times in this planner then come from your data.

  • Geofence-based Voyage report where a trip starts when the mixer leaves the plant geofence and ends when it returns, with the time it enters the site geofence.
  • Geofence movement details every entry and exit of each mixer at the sites you choose.
  • Live monitoring each mixer on the map with its status: moving or stopped.
  • Excel export of trip records, to compare with delivery tickets.
Questions

Questions about planning concrete trucks

Want the real delivery times of your truck mixers? Talk to Safee.

How many concrete trucks do I need for a pour?

Divide the truck's round trip time by the interval between trucks, and round up. The interval is the discharge time of one load at your placement rate. A 92-minute round trip with an 18-minute interval needs 6 trucks.

How long can ready-mix concrete stay in the truck?

Older editions of ASTM C94 set 1½ hours from mixing to the end of discharge. The current edition (C94/C94M-24d) leaves the limit to the purchaser, or to the producer when the purchaser states none. Many specifications still use 1½ hours and 300 drum revolutions, for example HCAI PIN 82 in California. Your project specification may set a different limit, especially in hot weather; enter that limit in the planner.

What placement rate should I use?

The rate your pump or crane and crew actually achieve on similar pours, not the pump's rated output. Placement often slows at the edges, around openings and when moving the pump.

Why are more trucks not always better?

Above the number needed, trucks only queue on site. The concrete in them gets older while waiting, and the time limit comes closer.

What happens when the pump breaks down?

Trucks already batched keep arriving. Use the stoppage fields on the Schedule tab to see which loads would go over the time limit, and how quickly the plant needs to stop batching.

Can I plan a pour fed by two plants?

Run the planner once for each plant with its own distance and share of the placement rate, then add the trucks.

How can I measure real delivery times?

Use the delivery tickets, or tracking data: a geofence around the plant and one around the site give the time each mixer leaves, arrives and returns.

Let's look at your plant numbers

Know where every mixer is and when every load arrives

Tell us how many truck mixers and plants you run and where you pour, and we will show you how Safee records each mixer's trip from the plant to the site and back.

Related tools and resources

Move on to your next fleet question